WWIS Header
Log in
updated 7:23 PM CDT, Oct 22, 2014

Repairs to Begin on Interstate 39-90

  • Written by Bob Gabrielson
  • Published in News

(5/15/14) One of Wisconsin's busiest interstates will be under construction starting next week.

 Pavement repairs begin Monday on Interstate 39-90 in both directions between Janesville and Edgerton.  All lanes will stay open during the day, with all lane closures coming at night.  Various ramps will close throughout the project.  The total cost is just under nine-million dollars, and it's expected to be finished in October.  Plans call for I-39-90 to eventually add lanes between Madison and Beloit at the Illinois line.

47°F

Black River Falls

Cloudy

Humidity: 65%

Wind: 5 mph

  • 22 Oct 2014 57°F 41°F
  • 23 Oct 2014 58°F 39°F